When Estimating Project Time Schedules Using Industry Standards, the Estimated

Question 104

Multiple Choice

When estimating project time schedules using industry standards, the estimated project completion time for a systems project would be _____ person-months if the actual planning phase were completed in 6 person-months.


A) 30
B) 40
C) 17.14
D) 9
E) 50