Michelle Has Decided to Use a Shortcut to Determine the Complexity

Question 38

Multiple Choice

Michelle has decided to use a shortcut to determine the complexity of the project she is currently managing. She has assigned the adjusted project complexity (PCA) a value of .65. She has determined that her project is _____.


A) bi-lateral
B) complex
C) microconvergent
D) normal
E) very simple

Correct Answer: