Jim Smith, the Project Manager for a High-Profile Project, Has

Question 40

True/False

Jim Smith, the project manager for a high-profile project, has permitted the users to add additional features to the systems project. The schedule and costs are now running over. This project suffers from poor standards.

Correct Answer:

verifed

Verified

Unlock this answer now