True/False
From a practical point of view, to estimate effort using use-case points, the use cases and the class diagrams must have been created.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q55: Project size is an important consideration in
Q56: Typically, a project will have one project
Q57: Typically, a technical lead is usually assigned
Q58: Jane, the head nurse on the surgery
Q59: The evolutionary Work Breakdown Structure makes it
Q61: A critical success factor for project management
Q62: Explain the three different aspects of a
Q63: The project team has just determined that
Q64: Give the formula for the schedule time
Q65: Explain the concept of timeboxing.