Multiple Choice
To complete a contract for fitting out a new shop in time for its opening, a refurbishment company has employed three temporary painters for 10 days at £45 per day and moved two carpenters who are paid £70 per day from another job for three days. The penalty for late completion of the shop is £300 but the delay to the carpenters' current job will only cost £150. What are the relevant costs?
A) £1,770
B) £1,800
C) £1,500
D) £1,650
Correct Answer:

Verified
Correct Answer:
Verified