A business plans to manufacture 400 watches a week, each taking 0.5 labour hours to produce. What is the total direct labour budget if the direct labour rate is £15 per hour and a pay rise of 12% is awarded three months into the year?
A) £156,000
B) £174,720
C) £173,550
D) £170,040