Multiple Choice
An informatics nurse is performing a cost-benefit analysis on the implementation of a health information technology. Which phase of the waterfall model is the project in?
A) Feasibility
B) Design
C) Implementation
D) Maintenance
Correct Answer:

Verified
Correct Answer:
Verified