Solved

(The Labour Hours That Should Have Been Used for Actual

Question 48

Multiple Choice

(The labour hours that should have been used for actual production - the labour hours that were actually used for actual production) x standard rate per hour. Which variance is calculated using this formula?


A) Direct Labour Efficiency Variance
B) Direct Labour Total Variance
C) Direct Labour Rate Variance
D) Variable Overhead Efficiency Variance

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge