Multiple Choice
Which one of the following is the correct formula used in calculating the variable overhead total variance?
A) What the actual direct labour or machine hours for actual production should have cost - what the actual direct labour or machine hours for actual production actually cost.
B) The total cost of variable overheads for actual production - the standard cost of variable overheads for actual production.
C) (Expected direct labour or machine hours for actual production - actual direct labour or machine hours for actual production) x the standard cost for one hour of variable overhead.
D) Standard expenditure on variable overhead incurred in actual production - (actual production units x standard variable overhead cost per unit of production) .
Correct Answer:

Verified
Correct Answer:
Verified
Q10: BFM Limited uses a standard costing system
Q11: The Pottery Limited uses a standard costing
Q12: What is the correct formula for the
Q13: XDT Limited uses a standard costing system
Q14: MSC Limited uses a standard costing system
Q16: ABC Limited uses a standard costing system
Q17: JMJ Limited operates a standard costing system
Q18: ZDT Limited uses a standard costing system
Q19: What is the correct formula for the
Q20: Podcaster University Press uses a standard costing