Multiple Choice
XDT Limited uses a standard costing system for all its services. XDT Limited services photocopiers. The standard direct labour time to service one photocopier is 2½ hours. Variable overhead is incurred at the rate of £5.00 per labour hour. The company budgets 750 photocopier services per month with budgeted monthly labour hours of 1,875. In September, XDT Limited serviced 800 photocopiers and paid their service engineers for a total of 1,950 labour hours. Actual variable overhead expenditure for the month was £9,550. What is the variable overhead efficiency variance for September?
A) £200 Favourable
B) £250 Favourable
C) £375 Unfavourable
D) £450 Favourable
Correct Answer:

Verified
Correct Answer:
Verified
Q26: ZTC Limited uses a standard costing system
Q27: Maria bakes and sells cakes for special
Q28: Maria's bakery bakes and sells cakes for
Q29: The Pottery Limited uses a standard costing
Q30: Potters Limited uses a standard costing system
Q32: ZDT Limited uses a standard costing system
Q33: The fixed overhead variance is calculated by
Q34: ABC Limited uses a standard costing system
Q35: Maria runs a bakery, baking and selling
Q36: Which one of the following scenarios would