Multiple Choice
The objective of ____ is to determine a specific value based on a predetermined discount rate.
A) project evaluation and review technique (PERT)
B) return on investment (ROI)
C) cost/benefit analysis
D) net present value (NPV)
Correct Answer:

Verified
Correct Answer:
Verified