menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Systems Analysis and Design Study Set 1
  4. Exam
    Exam 17: Project Management Techniques
  5. Question
    ​In Microsoft Project If Task B Need to Begin Two
Solved

​In Microsoft Project If Task B Need to Begin Two

Question 2

Question 2

Multiple Choice

​In Microsoft Project if task B need to begin two days after task A started,you would use a task dependency of _______.


A) FS + 2 days
B) SS + 2 days
C) ​FS - 2 days
D) ​SS - 2 days

Correct Answer:

verifed

Verified

Related Questions

Q1: ​Setting up a change control log to

Q3: ​The _ is the point at which

Q4: ​Which of the following equations is correct

Q5: ​Given the below figure what tasks are

Q6: ​Which of the following equations represents

Q7: ​In Microsoft Project a Tracking Gantt chart

Q8: ​The accumulation of yearly discounts based on

Q9: ​Which is NOT one of the characteristics

Q10: ​For a particular project the new system

Q11: ​In Microsoft Project the process (either manual

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines