Multiple Choice
Which of the following is a criticism of the World Bank's project cycle?
A) Restriction on the number of agents involved
B) Linear in orientation
C) No option for "abandonment"
D) No accounting of external influences
E) An under appreciation of policy evaluation
Correct Answer:

Verified
Correct Answer:
Verified