Multiple Choice
Which is NOT a criterion that is used to determine how to define tasks for a work breakdown structure.
A) How to know when the task is complete.
B) How to estimate the effort required.
C) A logical way to determine its predecessor.
D) It should take one to five days.
Correct Answer:

Verified
Correct Answer:
Verified