Multiple Choice
The technique whereby each task can be investigated by virtue of their most likely time to completion, their most optimistic time and most pessimistic time is referred to as ________________________?
A) The project analysis and review technique
B) The programme analysis and review technique
C) The project evaluation and review technique
D) The programme evaluation and review technique
Correct Answer:

Verified
Correct Answer:
Verified