Multiple Choice
If an operation has a design capacity of 168 hours, a planned downtime of 42 hours and an unplanned downtime of 6 hours, what is its efficiency?
A) 71.4%
B) 95.2%
C) 85.1%
D) 75.3%
Correct Answer:

Verified
Correct Answer:
Verified