Multiple Choice
Figure 1:
Figure 1 demonstrates an Excel spreadsheet that is used to model the following linear programming problem:
Note: Cells B3 and C3 are the designated cells for the optimal values of X₁ and X₂,respectively,while cell E4 is the designated cell for the objective function value.Cells D8:D10 designate the left-hand side of the constraints.
-Refer to Figure 1.What formula should be entered in cell D9 to compute the amount of resource 2 that is consumed?
A) =B9*D9 + C9*D9
B) =SUMPRODUCT(B2:C2,B9:C9)
C) =SUM(B9:C9)
D) =SUMPRODUCT(B3:C3,B9:C9)
E) =SUMPRODUCT(B9:C9,B5:C5)
Correct Answer:

Verified
Correct Answer:
Verified
Q4: A company that is introducing a
Q5: The constraint for a given resource is
Q6: A company manufactures four products A,B,C,and D
Q7: A linear programming model has the following
Q8: Suppose that a farmer has 5 acres
Q10: The simplex method is an algebraic solution
Q11: If a linear programming problem has alternate
Q12: In a product mix problem,a decision maker
Q13: _ systematically examines corner points,using algebraic steps,until
Q14: Consider the following linear programming problem.<br>