Multiple Choice
Which of the following statements about project crashing is False?
A) The overall project time is reduced by crashing activities on one or more critical paths.
B) It is best to crash an activity with the cheapest cost to crash per week.
C) As activities are crashed in a project network,it is possible for more than one path to be critical.
D) In order to reduce the overall project time,it may be necessary to crash more than one activity.
E) Project crashing problems can be solved using linear programming.
Correct Answer:

Verified
Correct Answer:
Verified
Q9: Use this information to answer the
Q10: A graph that plots the total resources
Q11: Use this information to answer the following
Q12: Suppose that the amount of time it
Q13: Use this information to answer the following
Q15: The crash cost per period is computed
Q18: In an Activity-On-Node (AON)network,arcs denote activities.
Q19: PERT is a probabilistic technique,whereas CPM is
Q22: Use this information to answer the
Q46: Use this information to answer the