Multiple Choice
If a company installs and tests only a portion of the new system, then repeatedly installs and tests portions of the new system until it is complete, this known as a ________ conversion.
A) phased
B) plunge
C) parallel
D) big-bang
E) pilot
Correct Answer:

Verified