Multiple Choice
In addition to estimating the time required for activities, advanced applications of PERT estimate the
A) job satisfaction associated with the task.
B) amount of resources to needed to accomplish the job.
C) productivity bonuses paid to workers who finish on schedule.
D) starting day of the project.
Correct Answer:

Verified
Correct Answer:
Verified