menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Modern Systems Analysis
  4. Exam
    Exam 3: Managing the Information Systems Project
  5. Question
    If an Activity's Optimistic Time Is 3 Months,its Realistic Time
Solved

If an Activity's Optimistic Time Is 3 Months,its Realistic Time

Question 140

Question 140

True/False

If an activity's optimistic time is 3 months,its realistic time is 5 months,and its pessimistic time is 10 months,then its estimated time would be 5.5 months.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q135: Indicating when and how written and oral

Q136: The third phase of the project management

Q137: A major disadvantage of the network diagram

Q138: One outcome of defining the overall system

Q139: The Project Scope Statement provides a detailed

Q141: _ is a controlled process of initiating,planning,executing,and

Q142: Working closely with customers to assure project

Q143: Critical path scheduling is a scheduling technique

Q144: The hallway discussion project team communication method

Q145: When using OOASD,iterations are generally meant to

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines