When comparing a Gantt chart to a network diagram,which of the following is a true statement?
A) Gantt shows the sequence dependencies between activities,whereas a network diagram shows the duration of activities.
B) A network diagram shows the time overlap of activities,whereas Gantt does not show time overlap.
C) Some forms of Gantt charts can show slack time available within an earliest start and latest finish duration,whereas a network diagram shows this by data within activity rectangles.
D) Both A and B
Correct Answer:

Verified
Correct Answer:
Verified
Q38: The project workbook serves as a repository
Q39: Managing the project team for effective team
Q40: Creating a work breakdown structure requires that
Q41: Task identification structure refers to the process
Q42: Skills that include defining and sequencing activities,communicating
Q44: An individual with a diverse set of
Q45: Project initiation is the second phase of
Q46: Which of the following is not a
Q47: Ensuring that all contractual terms of the
Q48: The status report project team communication method