    What Would Be the Estimated Time for Completion If the Time
Solved

What Would Be the Estimated Time for Completion If the Time

Question 21

Question 21

Multiple Choice

What would be the estimated time for completion if the time estimates for report design are as follows: optimistic = 3 weeks;pessimistic = 9 weeks;realistic = 6 weeks?


A) 3 weeks
B) 6 weeks
C) 18 weeks
D) 5 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q16: Having more iterations with fewer components to

Q17: A logic model is a graphical representation

Q18: In OOASD,it is better to make highly

Q19: A diagram that depicts project activities and

Q20: Influencing the activities of others toward the

Q22: With OOAD project management,during each iteration all

Q23: A planned undertaking of related activities to

Q24: A Project Scope Statement is developed during

Q25: The focus of closing the customer contract

Q26: Managing conflict within a project team to

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines