Multiple Choice
What would be the estimated time for completion if the time estimates for report design are as follows: optimistic = 3 weeks;pessimistic = 9 weeks;realistic = 6 weeks?
A) 3 weeks
B) 6 weeks
C) 18 weeks
D) 5 weeks
Correct Answer:

Verified
Correct Answer:
Verified