Multiple Choice
Slack time is equal to:
A) the difference between an activity's latest and earliest expected completion time
B) the latest expected completion time
C) the difference between the start time and realistic time for each activity
D) the sum of an activity's latest and earliest expected completion time
Correct Answer:

Verified
Correct Answer:
Verified