Multiple Choice
In OOSAD,one outcome of defining the overall system as a collection of components is:
A) a good system
B) the likelihood that components constructed earlier in the project will require greater rework
C) the likelihood that components constructed later in the project will require greater rework
D) the critical path will fail.
Correct Answer:

Verified
Correct Answer:
Verified