When conducting a technical risk assessment,which of the following is true?


A) A project has a greater likelihood of experiencing unforeseen technical problems when the development group lacks knowledge related to some aspect of the technology environment.
B) Large projects are riskier than small projects.
C) Successful IS projects require active involvement and cooperation between the user and development groups.
D) All of the above.