Multiple Choice
To gain an understanding of the likelihood that all potential time frame and completion date schedules can be met and that meeting these dates will be sufficient for dealing with the needs of the organization is the purpose of:
A) schedule feasibility
B) operational feasibility
C) technical feasibility
D) political feasibility