Multiple Choice
The delegator of construction duties remains liable if:
A) the delegatee performs the work properly, but the obligee did not approve of the delegation.
B) the delegatee performs the work improperly.
C) the obligee objects in writing to the delegatee's performance of the work, even if the delegatee performs the work properly.
D) the value of the contract is $500 or more and the delegatee performs the work properly.