Which of These Is Not Specified in a Gantt Chart

Question 19

Multiple Choice

Which of these is not specified in a Gantt chart?


A) policy or program activity
B) expected budget for each activity
C) person responsible for carrying out activity
D) time schedule for implementation and/or completion of each activity
E) all of the above are components of a Gantt chart

Correct Answer: