Multiple Choice
Which of these is not specified in a Gantt chart?
A) policy or program activity
B) expected budget for each activity
C) person responsible for carrying out activity
D) time schedule for implementation and/or completion of each activity
E) all of the above are components of a Gantt chart
Correct Answer:

Verified
Correct Answer:
Verified