Multiple Choice
A _____ is an important Scrum artifact used to graphically display progress on each sprint during the monitoring and controlling process.
A) WBS
B) sprint backlog
C) burndown chart
D) product backlog
Correct Answer:

Verified
Correct Answer:
Verified