Multiple Choice
_____ involves coordinating all planning efforts to create a consistent, coherent document.
A) Developing the project charter
B) Developing the preliminary project scope statement
C) Developing the project management plan
D) Developing the organizational process assets updates
Correct Answer:

Verified
Correct Answer: