    Knowing the Amount of Float Allows Project Managers to Know
Solved

Knowing the Amount of Float Allows Project Managers to Know

Question 85

Question 85

True/False

 Knowing the amount of float allows project managers to know whether a project schedule is flexible.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q80:  Project schedules grow out of basic documents

Q81:  After reviewing the project management plan, project

Q82:  In project schedule management, the next step

Q83:  A disadvantage of using Gantt charts is

Q84:  What is a network diagram? Describe two

Q86:  The final process in project schedule management

Q87:  A(n) _ for a project is the

Q88:  What is the latest possible time an

Q89:  In a network diagram, a(n) _ is

Q90:  A drawback of the precedence diagramming method

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines