Multiple Choice
In project time management, which of the following processes involve analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule?
A) Planning schedule management
B) Developing the schedule
C) Controlling the schedule
D) Defining activities
Correct Answer:

Verified
Correct Answer:
Verified