    In Project Time Management, A(n) _____ Is an Output of Controlling
Solved

In Project Time Management, A(n) _____ Is an Output of Controlling

Question 69

Question 69

Multiple Choice

In project time management, a(n) _____ is an output of controlling the schedule


A) activity duration estimate
B) project management plan update  
C) activity attribute
D) milestones list

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q18:  In a Gantt chart, thick black bars

Q26:  In a(n) _ relationship, the "from" activity

Q45:  A(n) _ is a schematic display of

Q67: The final process in project time management

Q68: Which of the following is a silimarity

Q70: In project time management, one should control

Q71: In project time management, the process of

Q72: In the activity defining process, the project

Q73: A(n) _ on a project is a

Q74: _ states that work expands to fill

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines