    In an AOA Network Diagram, _____ Occur When Two or More
Solved

In an AOA Network Diagram, _____ Occur When Two or More

Question 87

Question 87

Multiple Choice

In an AOA network diagram, _____ occur when two or more activities follow a single node.


A) combinations
B) buffers  
C) mergers
D) bursts

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q33:  _ is the number of workdays or

Q35:  The activity list should include the _,

Q40:  What are milestones? Describe.

Q58:  A drawback of the project management software

Q77:  In a critical path analysis, the shortest

Q84: Which of the following is a difference

Q85: After defining project activities, the next step

Q87:  A(n) _ for a project is the

Q89: In project time management, the process of_

Q90:  A drawback of the precedence diagramming method

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines