Which of the following is one of the main outputs of estimating activity resources process?


A) Project documents update
B) Milestone list  
C) Work breakdown structure
D) Activity duration estimate

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q22:  The critical path on a project can

Q32:  In a project schedule, the variable that

Q53: In project time management, the main goal

Q54: A difference between the Program Evaluation and

Q55: Which of the following dependencies involve relationships

Q55:  The arrows in a network diagram represent

Q59: _ provide(s) a standard format for displaying

Q61: In project time management, the ultimate goal

Q72:  In a network diagram, it is mandatory

Q80:  Project schedules grow out of basic documents

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines