Multiple Choice
After planning for procurement management, which of the following does the next process involve?
A) Determining the evaluation criteria for the contract award
B) Developing procurement statements of work
C) Using expert judgement in planning
Purchases and acquisitions
D) Sending appropriate documentation to potential sellers
Correct Answer:

Verified
Correct Answer:
Verified