Multiple Choice
Which of the following is not true regarding simulation?
A) It can be used to generate a probability distribution of NPVs.
B) It generates a probability distribution of NPVs by randomly drawing values for the input variable(s) .
C) It can only be used for one variable at a time.
D) It can be used to develop probability distributions of all variables with uncertain future values.
Correct Answer:

Verified
Correct Answer:
Verified