Multiple Choice
Carol and Bob enter into a contract for Bob to perform waste management services for Carol's commercial properties. Later, Bob alters a material term-increases the price-without Carol's knowledge or consent. She
A) can alter a material term, such as the payment date, without Bob's consent.
B) can treat the contract as discharged.
C) must adapt her performance accordingly.
D) must determine whether Bob's alteration constitutes substantial performance.
Correct Answer:

Verified
Correct Answer:
Verified
Q27: Delany & Sons, Inc., owes Evermore Bank
Q28: Ed's Electric substantially performs its contract with
Q29: A contract will be discharged if unforeseeable
Q30: Privity of contract establishes the basic concept
Q31: Lestor and MaryElise enter into a contract.
Q33: Renee contracts with Scott to pay him
Q34: When a party's performance is perfect, it
Q35: Drainage & Irrigation Equipment, Inc., contracts to
Q36: In most contracts, promises of performance are
Q37: Planners & Builders, Inc., enters into a