Multiple Choice
Contractors Service, Inc., enters into a contract to build a restaurant for Dierdre's Soup Spoons Bistro with Dierdre's payment due on August 1. On August 1, her bank is closed, and for this reason, she claims that she cannot pay on time. In this situation
A) Dierdre's bank is liable to Contractors Service.
B) Dierdre is in breach of contract.
C) the contract is discharged.
D) the contract is suspended.
Correct Answer:

Verified
Correct Answer:
Verified