Multiple Choice
According to Ohno and Toyota, _____ is a category of waste that uses more steps to produce a product than necessary.
A) excess inventory
B) defect
C) unnecessary movement
D) unnecessary transport
E) over-processing
Correct Answer:

Verified
Correct Answer:
Verified