In value stream mapping, the flow diagram that depicts process improvements to optimize the value and minimize the non-value-added streams is called a/an _____.
A) current state map
B) future/ideal state map
C) variation map
D) anticipated state map
E) None of the above.
Correct Answer:

Verified
Correct Answer:
Verified