Multiple Choice
Where one party prevents the other from completing the obligations under an entire contract, the party who has partly performed will be able to recover on what basis for the work already done?
A) Res extincta
B) Quantus quorum
C) Quantum meruit
D) the entire obligations rule
Correct Answer:

Verified
Correct Answer:
Verified