Multiple Choice
Until one knows otherwise
A) the Contract Administrator should consider any change a chance to improve profit
B) the Contract Administrator should consider any change a potential to affect the schedule
C) a change requires immediate resolution before it hinders group rapport
D) a change should be discussed at the next progress meeting
Correct Answer:

Verified
Correct Answer:
Verified