    The Longest Path Determines the Expected Time It Will Take
Solved

The Longest Path Determines the Expected Time It Will Take

Question 40

Question 40

True/False

The longest path determines the expected time it will take to finish the project, and this is called the critical path.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q35: What are the three main goals of

Q36: Larry was part of a project team

Q37: A project is a unique, repetitive, and

Q38: The optimistic time estimate is the best

Q39: Using the information shown in the previous

Q41: A(n) _ determines the timeline, sequence, and

Q42: Using the information shown in the previous

Q43: An important aspect of project closure is

Q44: Scope creep in a project is when

Q45: Using the information shown in the following

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines