If the length of the critical path is 25 weeks, what is the shortest project due date if the project manager wants at least a 98 percent probability that the project will be completed on or before the due date?
A) less than or equal to 25 weeks
B) greater than 32 weeks but less than 33 weeks
C) greater than 33 weeks but less than or equal to 35 weeks
D) greater than 25 weeks but less than 32 weeks