Solved

Given the Following Activities, Their Durations, and the Predecessor Relationships  Activity  Description  \begin{array}{c}\text { Activity } \\\text { Description }\end{array}

Question 74

Essay

Given the following activities, their durations, and the predecessor relationships, construct the network flow diagram and answer the questions that follow.

\begin{tabular}{|c|c|c|c|c|}
\hline  Activity  Description  \begin{array}{c}\text { Activity } \\\text { Description }\end{array} &  Immediate  Predecessor(s)  \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} &  Optimistic  (hours)  \begin{array}{c}\text { Optimistic } \\\text { (hours) }\end{array} &  Most Likely  (hours)  \begin{array}{c}\text { Most Likely } \\\text { (hours) }\end{array} &  Pessimistic  (hours)  \begin{array}{c}\text { Pessimistic } \\\text { (hours) }\end{array} \\
\hline A \mathrm{A} & - & 7 & 10 & 13 \\
\hline B \mathrm{B} & A \mathrm{A} & 5 & 11 & 23 \\
\hline C \mathrm{C} & A \mathrm{A} & 11 & 15 & 19 \\
\hline D \mathrm{D} & B \mathrm{B} & 4 & 5 & 6 \\
\hline E \mathrm{E} & D,C \mathrm{D}, \mathrm{C} & 9 & 11 & 25 \\
\hline F \mathrm{F} & C \mathrm{C} & 5 & 6 & 7 \\
\hline G \mathrm{G} & F \mathrm{F} & 5 & 5 & 5 \\
\hline H \mathrm{H} & F \mathrm{F} & 9 & 11 & 13 \\
\hline I \mathrm{I} & E,G,H \mathrm{E}, \mathrm{G}, \mathrm{H} & 7 & 11 & 15 \\
\hline J \mathrm{J} & I \mathrm{I} & 4 & 5 & 6 \\
\hline
\end{tabular}

A) What is the expected time for activity E?
B) What is the variance for activity E?
C) What is the critical path based on the calculation of the estimated times?
D) What is the estimated duration of the critical path?
E) What is the estimated variance along the critical path?
F) What is the probability of completion of the project before hour 45?

Correct Answer:

Answered by ExamLex AI

Answered by ExamLex AI

To answer these questions, we first need...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions