Essay
Given the following activities, their durations, and the predecessor relationships, construct the network flow diagram and answer the questions that follow.
\begin{tabular}{|c|c|c|c|c|}
\hline & & & & \\
\hline & - & 7 & 10 & 13 \\
\hline & & 5 & 11 & 23 \\
\hline & & 11 & 15 & 19 \\
\hline & & 4 & 5 & 6 \\
\hline & & 9 & 11 & 25 \\
\hline & & 5 & 6 & 7 \\
\hline & & 5 & 5 & 5 \\
\hline & & 9 & 11 & 13 \\
\hline & & 7 & 11 & 15 \\
\hline & & 4 & 5 & 6 \\
\hline
\end{tabular}
A) What is the expected time for activity E?
B) What is the variance for activity E?
C) What is the critical path based on the calculation of the estimated times?
D) What is the estimated duration of the critical path?
E) What is the estimated variance along the critical path?
F) What is the probability of completion of the project before hour 45?
Correct Answer:

Answered by ExamLex AI
To answer these questions, we first need...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Answered by ExamLex AI
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q69: Every project needs a superstar to be
Q70: Critical paths cannot change when we crash
Q71: _ is the art of orchestrating time
Q72: Projects with larger and longer deliverables are
Q73: Commuting to work and maintaining a website
Q75: Using the data supplied, what is the
Q76: Seeking improvement in any one dimension of
Q77: If the length of the critical path
Q78: Evaluation methods used for projects with cash
Q79: Evaluation methods used for projects with predictable