Multiple Choice
A standard form which records changes or extra work on a large project is called a:
A) job sheet
B) time sheet
C) delivery note
D) daywork sheet.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q5: Employers of companies employing more than five
Q6: Identify the non-statutory regulations from the following
Q7: A record which confirms that materials ordered
Q8: A diagram which shows the detailed connections
Q9: A standard form containing information about work
Q10: A standard form completed by every employee
Q11: Identify the statutory regulations from the following
Q12: A scale drawing showing the position of
Q14: A diagram which shows most clearly how
Q15: Everyone in the workplace has this responsibility