Multiple Choice
Which method relies on formulae and tables to estimate project costs (circle on) :
A) expert opinion
B) analogy
C) parametric
D) cost engineering
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q10: Statement: The feasible budget region is developed
Q11: Statement: Life cycle costs are the same
Q12: The estimate providing the best accuracy for
Q13: Statement: The parametric method of cost estimating
Q14: Statement: In general, high precision in an
Q16: Statement: The net present worth of the
Q17: Statement: When we speak of recurring costs,
Q18: Statement: If a cost estimate comes up
Q19: Statement: Generally the amount needed in the
Q20: Statement: The process of breaking the project