Multiple Choice
Which of the following are potential ways to reduce cost escalation (circle all that apply) :
A) using a fixed price contract
B) making estimates by people who tend to be optimistic
C) making final cost estimates at the earliest possible date in the planning process
D) monitoring and controlling project costs and activities
Correct Answer:

Verified
Correct Answer:
Verified
Q19: Statement: Generally the amount needed in the
Q20: Statement: The process of breaking the project
Q21: Statement: Life cycle costs refer exclusively to
Q22: Life cycle costs (circle all that are
Q23: Statement: The top-down approach to cost estimating
Q24: Statement: Life cycle costs are mostly determined
Q25: If the target cost is $235,000, which
Q27: Statement: Life cycle costs are estimated at
Q28: Statement: Working capital represents the difference between
Q29: Statement: Cost escalation always results in the